RCC Slab Material Estimator (Concrete, Steel, Cost)


Material estimate for a reinforced concrete roof slab: M20 concrete volume, cement bags, sand and aggregate, plus steel by the kg-per-m³ thumb rule, from the slab dimensions.

Enter the slab plan size and thickness.

Enter your values:
Results:

How it works

Concrete volume = length × width × thickness, split as M20 (1:1.5:3) with the 1.54 dry factor. Steel uses the site thumb rule of kg per m³ of concrete: about 75-80 for light residential slabs, 100 typical, 125 for heavier spans and loads.

  • Common slab thicknesses: 100-125 mm for rooms, 150 mm for heavier use; minimum per code and span.
  • Per m³ of M20: about 8 bags of cement, 0.42 m³ sand, 0.83 m³ aggregate, plus 75-125 kg steel.
  • Steel is quoted in kg; binding wire adds roughly 1% of steel weight.

Thumb-rule estimate for budgeting only - not a structural design. Slab thickness, span and reinforcement must come from a structural engineer to IS 456; the steel rule of thumb can be off by 30% or more on real designs.