How to Calculate Concrete Quantity and Cement, Sand and Aggregate


· CalculatorEdge Editorial Team

Ordering the right amount of concrete avoids both a short pour and a pile of waste. The work has two parts: find the volume of concrete the element needs, then split that volume into cement, sand and aggregate for a nominal mix. This article does both for a slab.

Formulas and units

  • Volume of a slab or footing: V = L × W × D, with all dimensions in m, so V is in m³.
  • Volume with waste: Vw = V × (1 + w), where w is the waste and spillage allowance, for example 0.05 for 5 percent.
  • Dry volume: Vdry = Vw × 1.54. Dry materials shrink when they are wetted and compacted, so about 1.54 times the wet volume is needed. Values from 1.52 to 1.57 are used.
  • Mix ratio c : s : a (cement : sand : aggregate), with total parts P = c + s + a. Cement volume = Vdry × c ÷ P, and likewise for sand and aggregate.
  • Cement mass: cement volume × 1440 kg/m³. Divide by 50 kg to get bags.

Assumptions

  • A nominal 1 : 1.5 : 3 mix by volume. This is a classic mix often called M20 in Indian practice. Your design may call for a mix by weight or a designed mix instead.
  • The dry volume factor is 1.54 and the bulk density of cement is 1440 kg/m³.
  • The slab is a plain rectangle with a constant thickness and no openings or thickened edges.

Worked example: a 6 m by 4 m slab, 150 mm thick

Volume: V = 6 × 4 × 0.15 = 3.60 m³.

With 5 percent waste: Vw = 3.60 × 1.05 = 3.78 m³.

Dry volume: Vdry = 3.78 × 1.54 = 5.82 m³.

Mix parts: P = 1 + 1.5 + 3 = 5.5.

  • Cement: 5.82 × 1 ÷ 5.5 = 1.058 m³. In mass: 1.058 × 1440 = 1524 kg, which is 30.5 bags, so order 31 bags of 50 kg.
  • Sand: 5.82 × 1.5 ÷ 5.5 = 1.59 m³.
  • Aggregate: 5.82 × 3 ÷ 5.5 = 3.18 m³.

For ready-mix concrete you simply order the wet volume, 3.78 m³ here. Suppliers often sell in steps, so ask for the minimum load and round up to the next step.

Tips for other shapes

  • Strip footing: V = length of trench × width × depth.
  • Round column: V = π × d² ÷ 4 × height.
  • Beam: V = width × depth × length, minus any part that lies inside the slab.

Limitations

The result is a take-off for planning and ordering. It does not design the mix or check strength. Real jobs also lose concrete to uneven subgrade, over-excavation and formwork leakage, so a 5 to 10 percent allowance is typical. Bulk densities and bulking of sand change with moisture, and modern practice favours a designed mix with a tested strength. Follow the structural drawings and the local code for the mix and cover.