Steel reinforcement is bought by weight, but drawings give bar diameter, spacing and length. To estimate cost and cutting lists you have to convert one to the other. This article shows the unit weight rule for round bars and a bar take-off for a slab.
Unit weight of a round bar
A round bar has a cross-section area of π × d² ÷ 4. With steel density of 7850 kg/m³ and the diameter d in mm, the mass per metre is:
w = π × d² ÷ 4 × 10−6 × 7850 = d² ÷ 162 (kg/m)
The constant 162 is rounded: 1 ÷ (π ÷ 4 × 10−6 × 7850) is about 162.2. Check for 10 mm: 10² ÷ 162 = 0.617 kg/m, and the exact value is 0.6165 kg/m.
| Bar diameter (mm) | Mass per metre (kg/m) |
|---|---|
| 8 | 0.395 |
| 10 | 0.617 |
| 12 | 0.888 |
| 16 | 1.579 |
| 20 | 2.466 |
| 25 | 3.854 |
Formulas for a slab bar grid
- Bars in a direction: n = floor((B − 2 × c) ÷ s) + 1, where B is the slab dimension across the bars in mm, c is the cover in mm and s is the spacing in mm.
- Length of each bar: the slab length minus cover at both ends, in mm. Add hooks, bends and laps if you detail them.
- Total length: the sum over both directions, converted to m.
- Total weight: total length × w.
Assumptions
- Plain round-section bar with a density of 7850 kg/m³. Ribbed (deformed) bars follow the same nominal weight formula.
- A single mat of bars in both directions, with the same diameter and spacing each way.
- No laps, hooks, chairs or bends are counted. Those are added as an allowance.
Worked example: 5 m by 4 m slab, 10 mm bars at 150 mm each way
Given: slab 5000 mm × 4000 mm, cover 25 mm, bars 10 mm at 150 mm centres in both directions.
Bars running along the 5 m side: they are spaced across the 4 m width. n = floor((4000 − 50) ÷ 150) + 1 = floor(26.33) + 1 = 27 bars. Each is 5000 − 50 = 4950 mm long, so the set is 27 × 4.95 = 133.65 m.
Bars running along the 4 m side: they are spaced across the 5 m length. n = floor((5000 − 50) ÷ 150) + 1 = floor(33) + 1 = 34 bars. Each is 4000 − 50 = 3950 mm long, so the set is 34 × 3.95 = 134.30 m.
Total length: 133.65 + 134.30 = 267.95 m.
Weight: 267.95 × 0.617 = 165.3 kg using the table value, or 267.95 × 100 ÷ 162 = 165.4 kg using the rule.
With allowance: add about 5 to 10 percent for laps, bends and cut waste, so order roughly 175 to 182 kg.
Limitations
This take-off follows a simple grid. Real drawings include extra top bars over supports, edge and corner bars, trimmer bars at openings, lap lengths from the code and bends with hooks. Weights per metre from a mill can differ slightly from the nominal values, with a tolerance set by the bar standard. Use the bar bending schedule from the structural drawings for ordering.
Try the calculators
- Rebar Calculator for weight from bar size and length, or a grid take-off from slab size and spacing.
- RCC Slab Material Calculator for slab concrete and steel quantities.
- Reinforcing Bar Development and Splice Lengths (ACI 318-05) for lap lengths.