How to Calculate Manufacturing Cost Per Part


· CalculatorEdge Editorial Team

Quoting a price, choosing between machines, or deciding whether a part is worth making in-house all start with one number: what does one part cost to make? The answer is a sum of five components, and each one has a clean formula. This article defines the components and works through an injection molding example end to end.

The five components

ComponentHow to compute it per part
Materialweight of material consumed per part (including scrap and runners) × price per kg
Machine timemachine hourly rate ÷ parts produced per hour
Laboreffective labor hourly cost allocated to the machine ÷ parts per hour
Overheadfactory overhead rate allocated per machine-hour ÷ parts per hour
Toolingtool cost ÷ total parts the tool produces over its life

Definitions and units

  • Cycle time: seconds per machine cycle. Output per hour = 3600 ÷ cycle time × cavities (parts per cycle).
  • Shot weight: total material injected per cycle in grams, parts plus runner system. Scrap and purge belong in material consumption too.
  • Machine hourly rate: the full cost of running the machine for one hour: energy, maintenance, depreciation or lease, and floor space if it is costed to the machine.
  • Tooling life: the number of shots a mold or die delivers before it is scrapped or rebuilt.

Assumptions

  • Steady production at the quoted cycle time, with no unplanned downtime (downtime is covered by OEE, see the limitations).
  • The runner is counted as consumed material; regrind credit would lower the material component.
  • Labor is allocated per machine; one operator tending two machines costs half an operator per machine.
  • All figures are illustrative, in dollars; the method is currency-independent.

Worked example: a molded PP container

Given: a two-cavity mold makes a 40.7 g polypropylene container with a 12 g runner, so the shot weight is 93.5 g. Cycle time is 22.5 s. PP costs $1.20 per kg. The 120-tonne machine runs at a $25 per hour rate, one operator at $8 per hour tends two machines, and factory overhead is allocated at $6 per machine-hour. The mold cost $12,000 and is rated for 500,000 shots.

Step 1, output: 3600 ÷ 22.5 = 160 cycles per hour, so 320 parts per hour.

Step 2, material: 0.0935 kg × $1.20 = $0.1122 per cycle, which is $0.0561 per part.

Step 3, machine time: $25 ÷ 320 = $0.0781 per part.

Step 4, labor: $8 ÷ 2 machines = $4 per machine-hour; $4 ÷ 320 = $0.0125 per part.

Step 5, overhead: $6 ÷ 320 = $0.0188 per part.

Step 6, tooling: 500,000 shots × 2 cavities = 1,000,000 parts; $12,000 ÷ 1,000,000 = $0.0120 per part.

Step 7, total: 0.0561 + 0.0781 + 0.0125 + 0.0188 + 0.0120 = about $0.177 per part, or 17.7 cents.

Quick lesson: machine time is the largest component here at 44 percent, and it falls directly with cycle time. Cutting the cycle from 22.5 s to 18 s raises output to 400 parts per hour and drops the machine, labor and overhead components by a fifth. This is why molders chase seconds.

Limitations

This is a steady-state model. Real cost also depends on utilization: a machine that only runs 70 percent of available hours spreads its hourly rate over fewer parts, which is what OEE measures. Scrap above the planned rate, quality failures, setup time between jobs, energy price swings and regrind credits all move the real number. For quotes, add a margin for these plus profit. For machining, replace shot weight with stock minus part weight and cycle time with machining plus loading time; the structure of the model is the same.

Try the calculators